Clearance from other cables :-
1. Power cable to Power cable - Clearance is not necessary. However, larger
clearance better would be current carrying capacity.
2. Power cable to control cable - 0.2 metre
3. Power cable to communication cable - 0.3 metre
4. Power cable to Gas / Water main - 0.3 metre
5. Power cable should not be laid above the telecom cable.
6. Size of the protection pipe (G.I) for the UG cable should be at least 1.5 times the outer dia. of
the cable.
For laying of HT UG 11KV , 3 core, Aluminium, armoured, XLPE cable :-
Approx. Dia. = 75 cm
Approx. weight = 634 kg
Bending Radius = 15 X Dia.
Minimum depth in laying Trench = 0.9 m
Cable route indicator for every 200 m and also at turning points.
Sand Filling min. 75 mm at the trench bottom and 75 mm additional covering.
1. Power cable to Power cable - Clearance is not necessary. However, larger
clearance better would be current carrying capacity.
2. Power cable to control cable - 0.2 metre
3. Power cable to communication cable - 0.3 metre
4. Power cable to Gas / Water main - 0.3 metre
5. Power cable should not be laid above the telecom cable.
6. Size of the protection pipe (G.I) for the UG cable should be at least 1.5 times the outer dia. of
the cable.
For laying of HT UG 11KV , 3 core, Aluminium, armoured, XLPE cable :-
Approx. Dia. = 75 cm
Approx. weight = 634 kg
Bending Radius = 15 X Dia.
Minimum depth in laying Trench = 0.9 m
Cable route indicator for every 200 m and also at turning points.
Sand Filling min. 75 mm at the trench bottom and 75 mm additional covering.